Project Milestones
This is currently how the project milestones look. Milestones are subject to change as the project and programme develop.
| Current Programme | |
|---|---|
| Winter 2011 | Completion of shell and core retail and catering areas in Forum building for fit-out (Section 2) |
| December 2011 | Main Library Level 0 Refurbishment complete (Section 5) |
| Spring 2012 | Forum Target completion date (Section 6) |
| Completed | |
|---|---|
| October 2007 - February 2008 | Desktop research, fact finding visits, focus groups, appointment of project manager and quantity surveyor |
| February 2008 | Scoping Conference |
| May 2008 | Issue draft design brief for review and comment |
| July 2008 | Design brief finalised for design competition |
| September 2008 | Design Competition Presentations Stage 1 (5 shortlisted Design Teams) |
| October 2008 | Design Competition Presentations Stage 2 (2 shortlisted Design Teams) |
| November 2008 | Appoint Concept Design Team |
| May 2009 | Planning Application Submission (revised date) |
| July 2009 | 3 Contractors shortlisted in competitive dialogue process |
| August 2009 | Enabling works commence |
| September 2009 | Planning permission granted (subject to 13 week planning period) |
| 26th February 2010 | Contractor tender return (for review by UoE) |
| 29th March 2010 | Main contractors start on site |
| 12th July 2010 | Commencement of Main Library refurb works |
| 7th January 2011 | Main Library Level -1 Refurbishment complete (Section 3) |
| Expected July 2011 | University Reception and Piazza target completion date (Section 1) |
| 15th July 2011 | Main Library Level +1 Refurbishment complete (Section 4) |