Essential repairs and improvements maps 2018/19

Some of our blocks at Lafrowda are undergoing essential repairs and improvement works during the 2018/19 academic year. The blocks directly affected will receive a rent reduction to acknowledge the impact the works will have on the students living in these residences.

Use the map below to see whether you have been allocated an affected block or a block in close proximity to an affected block.

Please be advised that whilst Chagford and Merrivale are not highlighted on the map below as being in close proximity to the Essential Repairs and Improvement Works scheduled for 2018/19, these residences will be in close proximity to development works for an extension of our student accommodation provision. More information about the Spreytonway development can be found on the Lafrowda, St.German’s and Residential Strategy webpages.

Please note blocks in close proximity will not be eligible for a rent reduction.

The information contained in this webpage may be subject to change.  We are seeking to provide you with as much detail as we are able to at this moment, however this could be changed by events outside the University’s control. For the avoidance of any doubt, the refund associated with the disruption will only be payable if the works proceed.

BlockDatesNature of work
C

Exterior works: September 2018 - March 2019

Shower room floor works: January 2019 - March 2019

Exterior works and shower room works are scheduled for this block during the dates highlighted
D

 Exterior works: September 2018 – March 2019

Shower room floor works: October 2018 – December 2018

Exterior works and shower room works are scheduled for this block during the dates highlighted
J February 2019 – March 2019 Shower room works are scheduled during the dates highlighted 
MA

Exterior works: September 2018 – April 2019

Shower room floor works: October 2018 – November 2018

Exterior works and shower room works are scheduled for this block during the dates highlighted
MB

Exterior works: September 2018 – April 2019

Shower room floor works: November 2018 – February 2019

Exterior works and shower room works are scheduled for this block during the dates highlighted
BlockDatesNature of works
B September 2018 – March 2019 Exterior improvement works are scheduled to take place on block C at Lafrowda which is in close proximity to this block
C September 2018 – March 2019 Exterior improvement works are scheduled to take place on block D at Lafrowda which is in close proximity to this block
Christow September 2018 – April 2019 Exterior improvement works are scheduled to take place on blocks MA and MB at Lafrowda which are in close proximity to this block
D September 2018 – March 2019 Exterior improvement works are scheduled to take place on block C at Lafrowda which is in close proximity to this block
E September 2018 – March 2019 Exterior improvement works are scheduled to take place on block D at Lafrowda which is in close proximity to this block
MA September 2018 – April 2019 Exterior improvement works are scheduled to take place on block MB at Lafrowda which is in close proximity to this block
MB September 2018 – April 2019 Exterior improvement works are scheduled to take place on block MA at Lafrowda which is in close proximity to this block
N September 2018 – April 2019 Exterior improvement works are scheduled to take place on blocks MA/MB at Lafrowda which is in close proximity to this block
P September 2018 – April 2019 Exterior improvement works are scheduled to take place on blocks MA/MB at Lafrowda which is in close proximity to this block
Q September 2018 – April 2019 Exterior improvement works are scheduled to take place on blocks MA/MB at Lafrowda which is in close proximity to this block
R September 2018 – April 2019 Exterior improvement works are scheduled to take place on blocks MA/MB at Lafrowda which is in close proximity to this block
Widecombe September 2018 – April 2019 Exterior improvement works are scheduled to take place on block MB at Lafrowda which is in close proximity to this block

 

All other blocks in the Lafrowda area are not in immediate proximity to the Essential Repairs and Improvement Works scheduled for the 2018/19 academic year.